Test Methodology Summary


  • Smoke or Sanity
    ** Non-extensive software testing, makes sure that the most crucial functions of a program work, but not bothering with finer details.
  • Unit
    ** Verify individual hardware or software units
  • Integration (Integ)
    ** Verify inter-unit and external interfaces
  • Functional (Func)
    ** Verify small groups of units and their interface ability to perform specific system and process functions
  • System (ST)
    Verify the complete system meets Func and Non-func Objectives and Requirements
    Functional ST includes: External Interoperability of all data and control elements
    Non-functional ST includes: Useability, Reliability, Efficiency, Portability, Maintainability
  • Performance (Perf)
    Covers Load, Volume, Stress and Exception testing
  • Regression
    Ensures that changes have not adversely affected the pre-existing system(s) or application(s)
  • User/Acceptance (UAT)
    Validates the complete and integrated system against acceptance criteria and customer expectations.
  • NOTE: Acceptance criteria are arrived at by aid of the System Requirements Specification (SRS), the Request For Proposal (RFP) and/or the Integration Test Plan (ITP)
  • Pilot/Field
    Verifies the complete system co-operates with business processes and workflow, to meet stakeholder expectations in a production-like environment.
  • Production Verification (PVT)
    A repeat of the Pilot testing but under full production and business conditions

Test Phases Explained


  • Smoke/Sanity Testing: Performed by developers before releasing the build to the testing team.
    May also be performed by testers to decide whether to accept the build for further testing or not.